Document Number |
Document Description |
Revision number |
Issue Purpose Code |
|---|---|---|---|
|
BCSM5-TCE-510-00-C-SPC-0018 |
RFQ FOR UTILITY & REBAR MAPPING AND STRUCTURAL INVESTIGATION OF EXISTING FOUNDATIONS AT PROPOSED PMR, RMHS SHED & DORE SLAG STORAGE SHED LOCATION |
A |
2 |
|
BCSM5-TCE-597-00-M-GDW-0002 |
General Arrangement Drawing of Storage Shed for Silica |
A |
1 |
|
BCSM5-TCE-510-00-E-SPC-0170 |
Technical specification for construction power at Truck Plaza |
A |
1 |
|
BCSM5-TCE-510-00-P-PIP-0002 |
PIPE ROUTING WITH TYPICAL CROSS SECTION OF PIPE RACK FROM SM-5 TO WTP,ASU AND ETP AREAS |
A |
2 |
|
BCSM5-TCE-597-00-M-GDW-0003 |
General Arrangement Drawing of Storage Shed for Limestone, Pig Iron, Barite and Qaurtz |
A |
1 |
|
BCSM5-TCE-510-00-P-RPT-0001 |
OPTION STUDY FOR PIPE ROUTING OF ACID AND UTILITY PIPES |
B |
1 |
|
BCSM5-TCE-594-XX-M-CAL-1076 |
Calculation sheet for Compressed Air System |
A |
1 |
|
BCSM5-TCE-510-00-E-SPC-0010 |
Detailed Electrical specification for EPC Packages |
C |
1 |
|
BCSM5-TCE-510-00-E-SPC-0152 |
TECHNICAL SPECIFICATION FOR DISTRIBUTION TRANSFORMER |
C |
1 |
Mail Identifier: 1013646146